Deployment Plan Form

1. Project Title: _____________________

2. Architecture (Readiness) Review Date requested: ____________________

Second date requested: _____________________________

3. Estimated Cost of Deployment:

A: Total Costs:

B: Hardware costs (itemized):

C: Software costs (itemized):

D: Internal headcount costs (estimated hours x $100/hour):

E: Other labor costs (e.g. hired from outside Cisco):

F: Travel costs:

G: Tools and parts costs:

H: Other costs (described):

4. Deployment Team:

Name:

Contact Phone:

Contact e-mail.

     
     
     

5. Microsoft Project:

If there are over 6 steps to the deployment process, attach the Deployment Plan steps in Microsoft Project form.

6. Location list:

List each physical location in order of deployment, and the planned date (or range of dates) for each location.

Location:

Date:

Other Info.

e.g. Brussels e.g. 4/24 - 4/30 e.g. Stage 1 router with E-1 card.
     
     

7. Deployment Steps:

Stage: 1 Work: e.g. Order all WAN circuits for Tier 1 (hub) locations
Step: 1 Responsibility: e.g. Project Manager (name).
  Tools Needed: e.g. Not Applicable (NA)
  Tools Present: e.g. (NA)
  Preceding steps: e.g. None.
  Following steps: e.g. Steps 4 - 17 require successful WAN circuit installation.
  Duration: e.g. 45 days, according to circuit vendor.
  Start/end dates: e.g. Order April 5th, Deliver by May 20th.
Stage: Work:
Step: Responsibility:
  Tools Needed:
  Tools Present:
  Preceding steps:
  Following steps:
  Duration:
  Start/end dates:

8. Deployment Templates:

A: Hardware, Software: Describe or show diagram of new architecture and connections. Respond for each stage. __________________________________________________________________

B: Configuration, Scripts: Attach copies of the configuration files or scripts which will be loaded at each site type, based on the Architecture Plan.

9. Contingency (backout) Plan:

Describe: _____________________________________________________

10. Deployment Training:

Yes

No

Description of your Project: My project …

    I verify that each person deploying this equipment / software / configuration in the production network has had at least one prior dry run session deploying identical network elements in a lab environment.

If No, explain why: ____________________________________________________

 

Submit Form | Clear Form


Path: http://eman/ANTS/Documentation/policy-procedures/stage_three/docs/deployment_plan_form.html
Owner: Pete Feighner, pfeighne@cisco.com
Last Modified: December 09, 1998
This is an sns-docs controlled document. Uncontrolled if printed.

Copyright © Cisco Systems, Inc. 1998